Community Road Projects

Jun 20, 2019

With the current community paving projects underway, contractors are asking for your assistance to help make the process as smooth as possible.

Residents are asked to remove all vehicles parked on Celebration Avenue between Waterside and the end of Celebration Avenue in Artisan Park. Vehicles left along the route could be damaged as a result of the ongoing work.

Also, drivers are asked to obey all flag and traffic personnel and please slow down when entering and traveling in the work zones. In addition, alternate traffic patterns will be in effect during the road work, so please use caution.

Your assistance and cooperation is appreciated.

 

As a reminder:

Tentative summer road paving schedule in the community (pending no weather or equipment related issues)

Celebration Avenue

  • Waterside Drive to South dead end
  •  Through July 2 (no weekends)

Waterside Drive

  • Celebration Avenue to Celebration Blvd
  • July 8 through July 12 (no weekends)

Celebration Blvd

  • Campus Street to 1390 Celebration Blvd
  • July 15 through August 2 (no weekends)

The county is requesting that no vehicles be parked on roadways during the time frames mentioned above. Contractors will be utilizing the parking stalls as travel lanes in order to keep traffic moving, keeping any delays at a minimum.