Longmeadow Playground Repair Update

The Longmeadow Playground Repair project is tentatively scheduled to begin on Thursday, March 13th. Before work begins, the Maintenance Team will install a safety fence around the playground. The project will involve removing and replacing the existing artificial turf and safety surface, relocating the merry-go-round, and installing new and replacement equipment, including sensory features, swings, and pod climbers. We will provide further updates on timelines and closures as the project start date approaches.

Playground Shade Canopy Installation Updates

Playground shade canopy structures for East Village, East Crescent Park Playground, and Island Village, Magnolia Square are in progress. The East Village playground shade canopy is expected to ship next week. In preparation for installation, the existing small tin roof on the playground will be removed and the columns capped off. The Island Village shade structure is currently being manufactured and is approximately one month behind the East Village shade structure’s progress.

Dog Park Renovation Update

At Wednesday’s Board meeting, the Board approved a proposal to replace the sod at both Dog Parks and to create an octagonal digging pit in the Large Dog Park. Work is scheduled to begin on Monday, March 10th. Below is a tentative outline and description of the project:

  • Phase 1: Dual Park Closure (8 Days)​
    • Dates: Monday, March 10th – Monday, March 17th​
    • Action: Closure of both the Small and Large Dog Parks for initial renovation work. 
  • Phase 2: Small Dog Park Renovation & Limited Large Dog Park Access (4 Weeks)​
    • Dates: Tuesday, March 18th – Monday, April 7th 
    • Action:​
      • Closure of the Small Dog Park for sod installation and root establishment. 
      • Large Dog Park: Split use schedule:  
      • 4 days per week: Large dogs only. 
      • 3 days per week: Small dogs only. 
  • Phase 3: Large Dog Park Renovation & Small Dog Park Reopening (4 Weeks)​
    • Dates: Tuesday, April 8th – Monday, May 5th​
    • Action:​
      • Reopening of the Small Dog Park with split use schedule: 
      • 3 days per week: Large dogs only. 
      • 4 days per week: Small dogs only. 
      • Closure of the Large Dog Park for sod installation and root establishment. 
  • Phase 4: Full Park Reopening (Normal Operations)​
    • Date: Tuesday, May 6th 
    • Action:​Reopening of the Large Dog Park and return to normal, unrestricted operations for both parks. 

Lakeside Splash Pad Update

The Lakeside Splash Pad Project is the first initiative outlined in the Master Plan Advisory Group’s final recommendations to the Board. The Master Plan Advisory Committee, in collaboration with Management, successfully conducted an RFP process that led to the selection of a vendor for the project. During Wednesday’s Board meeting, the Board approved SplashPad USA as the vendor to install the new Splash Pad at Lakeside. This Splash Pad will replace the Kiddie Pool, which is currently in disrepair and needs to be replaced. While a start date has not yet been set, we will keep the community informed as the project progresses.

Pool Resurfacing Update

The resurfacing of the North Village Pool is complete, and the curing process is nearly finished. The pool is scheduled to reopen on Wednesday, March 5th.

The resurfacing of the Spring Park Pool is also complete and currently curing, with a planned reopening on Friday, March 7th. In efforts to work towards continual access to community lap lanes, the closure of Lakeside Pool, originally scheduled for Monday, March 3rd, will now be delayed until Friday, March 7th. While this is an accelerated schedule for the curing process, please be advised that the opening date is subject to delays if the pool clarity and chemical levels do not reach the necessary safety standards.

Pool Light Replacement at North Village & Spring Park Pools

The interior pool lights at North Village and Spring Park pools have not been able to be repaired or have their bulbs replaced. A full replacement of the interior lights, which includes replacing the fixtures, is outside the scope of the pool resurfacing project and represents a significant expense.

Due to the cost implications, the pool light replacement is scheduled to be reviewed by the CROA Board as an action item in the March 12th workshop. This may result in modified hours of operation in the evenings until the approval and replacement of the pool lights can take place.

Pool House Restroom Renovations Update

Next week, contractors will begin staging equipment for restroom renovations at the Lakeside and Spring Park Pool Houses. Additional information about these renovations will be shared soon. Efforts will be made to minimize any disruption to pool access.